Two months after starting construction, PVC-MS has finished 50 % of workload, 14 days ahead of the plan. The fabrication of Panel row 2 also was finished. As schedule, panel row 2 is erected at the end of May and the jacket is loaded out on 10th August.
Petronas Carigali Vietnam Limited (PCVL) is the investor of the 57-million-USD project, including a jacket with 2.350 tons and topside of 2000 tons.. PVC-MS is the general contractor in charge of engineering, procurement, construction and commissioning (EPCC).
On behalf of PVC-MS, Director Nguyen Dinh The affirmed that Diamond Project will done with highest safety, quality, and strict adherence to deadlines.
The project is expected to begin operating on May 19, 2014.