Thien Ung’s jacket weighs 6,330 tons, including: jacket, boat-landing, conductor, buoyancy tank and PVC-MS has commenced project from May 2014 then on 28th March 2015, has successfully rolled up Panel Row 1 part 1 Thien Ung’s jacket. So far, following the successful of construction Panel Row 1 part 2, PVC-MS has completed the fabrication, fitting and erection Panel Rows.
During project implementation, PVC-MS ensures absolute safety work, organization of human resources appropriate to the project being implemented on schedule, quality as required by Client.
PVC-MS currently is arranging employees working two shifts constantly per day, urgently implement the ground works and complete erection as well as the remaining items to promptly hand over to the Vietsovpetro in mid of June 2015 to bring offshore installation.
PVC-MS