Living quarter module, which is contained in Su Tu Trang Living quarter project, includes 4 main decks with a total weight of over 500 tons, equipped with such items: Heliport, bed room, dining room, living room, kitchen area... According to the plan, the Living quarter module will be erected into Su Tu Trang topside in May, 2016.
Su Tu Trang Living Quarter project is a part of Su Tu Trang development plan Phase 1, in which Cuu Long Joint Operating Company (Cuu Long JOC) is the investor, PTSC is the general EPCI contractor, and PVC-MS is the construction contractor.
After 5 months of implementation, PVC-MS has completed 32.38% of workload so far, exceeding the set standard by 3.4%. Currently, the Company is promptly making Panel row A, Panel row B and Elevation frames of Jacket. As for the topside, PVC-MS has finished assemling Sub-Cellar Deck and Cellar Deck. The Intermediate Deck and Main Deck is being urgently constructed and will have been erected into Su Tu Trang topside by the end of January 2016.
It is expected that PVC-MS will accomplish the whole project in August 2016 to be ready for offshore installation.
PVC-MS