Su Tu Trang living quarter, commenced in August 2015, is a part of Su Tu Trang development plan Phase 1 of Cuu Long Joint Operating Company (Cuu Long JOC). PTSC M&C is assigned to be the EPCI general contractor, and PVC-MS is the EPC contractor.
Su Tu Trang living quarter has a total weight of 4,500 tons. PVC-MS’ estimated time of construction is 12 months.
After 3 months, PVC-MS has done 13% of the workload, catching up the schedule. Work safety is guaranteed entirely. As soon as Sub-Cellar Deck has been successfully installed, PVC-MS is now urgently executing the Cellar Deck and Main Deck for Su Tu Trang living quarter. It is expected that PVC-MS will have completed the onshore construction by the end of July 2016 and handed it over to the General contractor.