After 04 months of implementing the JA&KA Gallaf 3 Jacket Project, on 07-Sep-2022, at the port of Petroleum Equipment Assembly and Metal Structure (PVC-MS) at No. 65A, 30/4 Street, PVC-MS successfully completed the roll-up of Panel Row B – the first Panel of JA jacket. Subsequently, on 13-Nov-2022, Panel Row A of KA jacket was also successfully rolled up at the PVC-MS’s port.
Panel Row B- JA Jacket and Panel Row A - KA Jacket were successfully rolled up
Both Panel Row B - JA jacket and Panel Row A - KA jacket have a total weight of 483.5 tons, accounting for 10.865% of the total weight of the JA&KA project. These are the first 02 crane codes to be rolled up of JA&KA Gallaf 3 Jacket Project.
Panel Row B- JA Jacket was rolled up on 07-Nov-2022
Panel Row A- KA Jacket was rolled up on 13-Nov-2022
Present and witnessing the roll-up of 02 panels of JA and KA jackets at PVC-MS port, Mr. Shanthakumar Rajenthrans, the representative of NOC’s management for Gallaf 3 Project in Vietnam, stated that 10 months before, NOC had had some concerns during the survey of the infrastructure and systems of PVC-MS. However, driven by the desire to collaborate and the achievements in implementing jackets of PVC-MS over the years, NOC had decided to cooperate with PVC-MS on the two JA & KA jacket project. That day, with the successful roll-up of the first 02 panels, ensuring progress, quality, and safety as required, PVC-MS affirmed its capabilities and changed their perspective. NOC had been, was, and would always be ready to support PVC-MS in the most effective implementation of the 02 JA & KA jacket project. In the future, if NOC had new projects to deploy, PVC-MS would be one of NOC's priority choices.
Mr. Shanthakumar Rajenthrans - The representative of NOC’s management for Gallaf 3 Project in Vietnam at PVC-MS’s construction site (orange shirt)
The successful roll-up of the 02 panels, on schedule and following extremely stringent technical, quality, and safety requirements, garnered great satisfaction from the Investor NOC and the General Contractor PTSC M&C, creating favorable conditions for PVC-MS in the upcoming project milestones.
The Investor NOC took commemorative photos with the leadership of PVC-MS at PVC-MS’s construction site
Currently, the construction progress of the JA is at 53.71%, and the KA jacket is at 50.75%, meeting the schedule approved by the Investor. PVC-MS is actively adhering closely to the project milestones and ensuring to meet all requirements of the General Contractor and the Investor.
Aerial picture of Panel Row B- JA Jacket being rolled up
PVC-MS