The two WHP- Thang Long - Dong Do jackets of Thang Long – Dong Do field development project are of Block 01/97 and 02/97, in the Cuu Long basin of the continental shelf of Vietnam. In particular, WHP-Thang Long with a jacket weighed 1,847 ton, two boat-landings with weight of 243 tons and 1,199 tons of piles. WHP-Dong Do has a weight of 1866 -ton jacket, two 265-ton boat-landings and 1236 tons of piles.
These are the oil and gas projects implemented at the 60m -70m depth, with the very tight construction schedule. Fabrication of WHP-Thang Long jacket will be implemented in the duration of 10 months and WHP-Dong Do jacket will be implemented in 11 months.
Mai Phương