This is a wellhead platform’s jacket in Dragon field and is a key project of PetroVietnam.
RC7 jacket was constructed from on 10 March 2011, in which PVC-MS implements: jacket, vessel holding frame, conductor tubes, with a total weight of 1,200 tons.
During construction, on Vietsovpetro Yard, there are many big projects are implemented. So PVC-MS and Vietsovpetro to build and apply a process of making alternate items stand structure, shortening construction time, saving labor and duration of the project.
PVC-MS had mobilized 200 employees, with more than 180,000 safety hours for construction of RC7 jacket. Vietsovpetro has checked and took over the work with technique, quality and progress.
RC7 jacket is installing in Dragon field.
PVC-MS