This exploitation rig invested by Vietsovpetro, PVC-MS is a subcontractor of construction.
RC 6 Rig’s jacket has a total weight of 2,000 tons, was started of construction on May 02/2011.
Until now, PVC-MS has made 66% of workload. The company are urgently madding Panel Row A, vessel counter, pipe and conductor pile.
Expected, in the first of June 2011, Panel Row A will be erected and on 1st July 2011, PVC-MS will complete and hand over RC 6 to the investor.
PVC-MS