Te Giac Trang Wellhead Platform Topside H4 valued 44 million US; total weight structures, systems and equipments of about 2500 tons. This is the first epCI (Design, Procure, Manufacture and Install) contract of PVC-MS and also the first work in Sao Mai Ben Dinh Petroleum Fabricant and Equipments Yard.
Take a role of general constructor; PVC-MS has used 100% lifting devices of the Company to erect the floor, instead renting devices before.
After four months of construction, PVC-MS has completed fabrication of the main structure, reaching 35% of workload, exceeding 4% of the plan. Under the plan, in May 2012, PVC-MS will complete fabrication on shore, before install off shore, and make sure that exploitation platform H4 will receive the fist oil flow in August 2012.
PVC-MS