Su Tu Trang Jacket was started from late October, 2015. Total weight of the jacket is 2,000 tons, inclusive of piles and boat-landing. This is a part of Su Tu Trang living quarter project comprising topside, jacket, living quarter module, and helipad. The whole project approximately weighs 4,500 tons.
Over more than 3 months of construction, PVC-MS has completed 35% of workload of the jacket, exceeding the plan by 15%. Panel row A was successfully built and continued to assemble into the composition of Su Tu Trang jacket. The company is now focusing on elevation frame, Panel row B, caisson drain pipe and auxiliary items. As scheduled, the Panel row B construction will be carried out from January 30. With current progress, PVC-MS will have finalized Su Tu Trang jacket by July 15.
PVC-MS